The Council of Torres Novas yesterday unanimously approved the opening of the procedure to declare null the prior information in favor of the installation of a biomethane unit in Árgea, on the grounds that it contravenes the Municipal Master Plan (PDM).
“We understand that we are in the presence of a null act,” said the president of the Council, José Trincão Marques (PS), at the public meeting of the executive, adding that the proposal was analyzed by the municipal services of urban planning, planning and legal affairs.
The deliberation provides for notifying the promoter Gasdaterra, which will have 30 days to respond in writing in a preliminary hearing, with the intention of declaring nullity becoming definitive if the company does not submit any comment.
At issue is the prior favorable information issued by order of 14 May 2025 and ratified by the Council on 21 May of the same year, in the previous term, for the installation of the unit in the Union of Parishes of Olaia and Paço, in the municipality of Torres Novas, district of Santarém.
According to the proposal, the technical information that supported the decision applied to the site a classification that allowed construction where the Municipal Master Plan (PDM) did not foresee that possibility, also contravening a provision that prohibits, at that location, renewable energy production units subject to environmental impact assessment.
The municipal services argue that the prior favorable information was conditioned on compliance with the PDM, but that this condition would require an amendment to the plan itself.
Trincão Marques explained that the decision was supported by technical and legal analysis, involving specialists in administrative and urban law, and that the municipality only moved forward after gathering sufficient grounds.
“We only moved forward with this after we had solid grounds that we could do it and we do have them,” he said, noting that the declaration of nullity also constitutes “one of the ways […] to prevent the installation” of the unit in Árgea.
The executive also decided to inform the Public Prosecutor’s Office of the facts, assess potential civil liability of the municipality, and communicate the decision to the entities responsible for licensing procedures and environmental assessment, so that they do not consider the favorable opinion as proof of the project’s urban-planning conformity.
Despite the unanimity, the PSD councilor Tiago Ferreira presented a declaration of vote to justify the support given to the prior favorable information in May 2025.
The councilor explained that he voted in favor because he believed there was a commitment by the previous Socialist administration to advance provisional measures of territorial planning that would allow overcoming the incompatibility with the PDM.
“There was a commitment to enact provisional measures,” he said, recalling that this possibility was associated with the decision taken in the previous term.
Gasdaterra plans to invest about 18 million euros in a unit with the capacity to treat approximately 100,000 tonnes per year of organic waste and livestock effluents, whose location has been contested by residents and by councilors of Torres Novas and the neighboring Entroncamento.
Opponents point to the proximity of dwellings and express concerns about odors, increased heavy traffic, and potential effects on water resources.
The company had previously told Lusa that the location was chosen after analysis of alternatives and that the project includes odor-control measures and protection of water resources, linking the installation to the valorisation of waste and to the production of renewable energy.
The public consultation promoted by the Portuguese Environment Agency ran from 13 May to 03 July, within the scope of the environmental impact assessment of the project.
In the same meeting, the Council also unanimously approved that the two ordinary monthly meetings be open to the public, instead of only one.